Integration testing
Post-Commissioning Integration Tests
Integration testing verifies end-to-end functionality after commissioning. The test sequence starts with cell on-air verification — confirm the cell is broadcasting SSB (Synchronization Signal Block) and visible to a test UE. Next, registration test: the UE successfully attaches to the new cell and receives an IP address via PDU session establishment. Voice call test verifies VoNR or EPS Fallback call setup, audio quality (MOS above 3.5), and call release. Each test must pass before proceeding to the next, as later tests depend on earlier functionality being correct.